Spur Ranch Road Schedule Update

Dear Neighbors,

 

Bob Sherwin phoned me this afternoon with a revised schedule of the road rework. Basically, the schedule has slipped a few days so that Michael McDermott, CEO of RP International, can oversee the work. McDermott is flying here from Manila and is scheduled to arrive on Monday, Jan. 9.  Here’s a day-by-day breakdown of the planned work, as of this afternoon, and I’ll let you know if there are any further changes.

 

Monday (1/2): A grader will scoop the dirt currently piled on the sides of the road, use it to fill in ruts and potholes in the road,and make the road as driveable as possible. (This is the same as the previous plan.)

 

Thursday (1/5) to Saturday noon (1/7): 1200 tons of the new clay mix will be delivered, piled in a 4 ft wide swath along one edge of the road. There will be five or six dump trucks delivering the mix throughout this 2.5 day period. The remainder of the road will be open for traffic.

 

Monday (1/9): Reconstruction of the road will begin in the morning, to last 4-5 days. Michael McDermott, CEO of RoadPacker Int’l, will be here from Manila to oversee the work. Flaggers with walkie-talkies will be needed for this period only. Let’s hope the weather holds out.

 

Regards,

Jim

 

 