Dear Neighbor,
The work on our road was postponed for a few days because of the rain (1.25 inches recorded at my house). The road is still a bit too wet, but work will resume this Wednesday, barring additional rain. As of today, the only work completed has been unloading of several truck loads of basecourse over a few hundred yards on the bad washboards East of Calle Junipero. The new bascourse has only been smoothed along the road surface to permit traffic to pass. It will be shaped, graded, and compacted once work resumes. As a reminder, it will probably take four days or so to complete work along the road.